Construction structure form of fir wood piles for river piling
- 2018-12-19-

River piling fir wood pilesIt is a kind of wooden pile used to protect the river. It can tighten the river bed soil and play a positive role in preventing water and soil erosion. ThenRiver piling fir wood pilesHow do you need to use it? How to maintain the storage before use?

Build various waterside buildings,River piling fir wood pilesAnother major role of water is to build various underwater buildings, giving them a stress point, and ensuring that they remain stable and incorruptible for a very long time. Therefore,river fightpileChinese firpileGenerallyChoose trees such as fir piles and pine piles, which have better anti-corrosion properties and are suitable for use in this environment.

One, this timeRiver piling fir wood pilesConstruction project overview:
River water conservancy slope protection project



2,River piling fir wood pilesConstruction structure form:
According to the design, the river slope protection requires the use of fir pile slope protection solutions. Use an excavator to drive the fir piles underground to expose 1000px of the water surface.
3,River piling fir wood pilesSelection of Slope Protection Plan for Treating Soft Foundation
A combination of silt, silty soil, miscellaneous fill soil, etc. is called a weak soil system. The weak soil foundation is composed of a weak soil system. The weak soil foundation on the river bank must be reinforced or improved with fir piles according to requirements to increase the bearing capacity and ensure Soft soil foundation is stable.
In actual operation, there are many examples of general river slope protection projects mainly using fir piles.
4,River piling fir wood pilesGround construction treatment design
useRiver piling fir wood pilesThe diameter is 12 centimeters and the length is 4 meters. Plum blossom piles are used for piling.
5,River piling fir wood pilesGround construction treatment methods
(1) First dig out the upper gravel, and then carry out the fir pile driving construction. During the fir pile construction, the fir piles need to be stabilized to the old soil layer.
(2)River piling fir wood pilesAfter the construction is completed, the river bank will be flattened and planted with greening.


Shanghai Lanxiao Industrial Co., Ltd.

contact us

    Contact person: Lin Jianhong
    Phone: 13918478586

    QQ:371225501

    WeChat:15921183117
    Email:371225501@qq.com
    Address: No. 8365, Chuannanfeng Highway, Fengxian District, Shanghai

Mobile