Design of using gabion net on revetment fir wood piles 2
- 2019-06-20-

Gabion mesh is used inrevetment cedar pilesScheme design 2

The construction process of slope protection gabion retaining wall is mainly divided into the following contents:

1. Choose gabion mesh products of appropriate specifications for slope protection. Generally, the gabion specifications are 15003000600, 30001500600mm; pad 30001500400mm; the grid pattern is 951500. Because the wire mesh products of this specification have moderate diameter and different In the dog cage, various green plants are planted, and the green environment also plays its role, but it also integrates the environment and the local area.

2. Choose a good gabion product. When the construction starts, first clear the base. This base is a basic retaining wall project base that needs to be established. During the process of the base of the retaining wall project, eliminate the basics of dirt removal. Eliminating the dirt in the basic memory will affect the reliability of the gabion retaining wall, so it is a basic task that must be eliminated.

3. The slope protection around the foot protection shall be repaired and compacted according to the designed slope slope to make the slope protection dense, flat and stable. Spread 300g\/m1 anti-seepage geotextile under the slope protection, with one side of the anti-seepage geotextile Press into the concrete structure foot guard 014m, and lay the other end horizontally along the leveled slope protection, and overlap the steel bars adjacent to the anti-seepage geotextile according to the design plan. Pave 0.3 on the anti-seepage geotextile. m thick sand gravel foundation cushion.

11. Complete the basic work and install the anti-seepage geomembrane, which can assemble the cage. I think assembling the cage is a very simple matter, just open the grid center and connect with the convergence to create a The ties are 30cm each, and the work of the cage parts is completed.

4. After the wire cage is assembled, it can be filled with "stones". At this time, stones that meet the requirements need to be filled into the cage.

6. After the above work is completed, it is very important to deposit the reinforced retaining wall and keep the wall reinforcement work. If the retaining wall is too high, ensure that the reinforced retaining wall reinforcement connection is used.


Shanghai Lanxiao Industrial Co., Ltd.

contact us

    Contact person: Lin Jianhong
    Phone: 13918478586

    QQ:371225501

    WeChat:15921183117
    Email:371225501@qq.com
    Address: No. 8365, Chuannanfeng Highway, Fengxian District, Shanghai

Mobile